We were asked to do a turn-key install for a 75kwp solar array at the prestigious Trinity House.  This was our most challenging job to date; the building was between 12 and 20 meters high, and it was not possible to use scaffolding. Therefore the job was done using Mansafe systems and harnesses, using scissor lifts and cherry pickers for access. We had to do a lot of specialist training to satisfy the very strict health and safety requirements for this contract.  We completed the job before the deadline and with plenty of time to commission. Trinity house now has a maintainable roof that will generate around 70Mwh/ year.   